[Music] hi Timothy Robbins construction division manager city of broken Aro you're back on site with me here on our 23rd Street widening project between 71st and 81st in eastern broken Aro so over the last 30 to 45 days our contractors been making a lot of progress along this mile section and very specifically at that bridge over Highway 51 they've done a great job in getting the beams in and getting the decking in over top of of the roadway in preparation for their first concrete placement on the bridge decking itself is scheduled for about mid-march so kind of be looking for that there's going to be a lot of uh activity going around that bridge so just kind of keep that in mind going down Highway 51 now also the contractor has started working on the uh Northbound section of 23rd Street and that is on the east side and they have actually cut this down to grade from uh Houston all the way up up to kosha now so they'll be working on that over the month of March and getting that soil stabilized getting the storm sewers in and then they're looking to start Paving operations on the east side of 23rd starting in around mid April so now on Houston in the month of uh March they will be looking to start the pavement on the north side of the Houston intersection at the intersection with 23rd so when that happens kind of keep an eyee out for traffic movement they'll be putting traffic on the newly constructed portion of the intersection and uh the speed limits will still stay the same and the no leftand turns North and South will also be in place until the end of construction contractors making great progress we're looking to still have the completed overall project in early summer this year so thank you for your patience appreciate you have a great day